The posts describe Nebius’s Q3 2026 results as strong, citing revenue of about $981 million, up 571% year over year, and adjusted EBITDA of about $466 million. They also cite a $37.5 million net loss, diluted GAAP EPS of -$0.13, operating cash flow of -$273 million, and $7.4 billion in cash. These figures, estimates, and comparisons should be checked against the company’s earnings release and filing, according to @wallstengine and @StockSavvyShay.
The posts say ARR was $6.4 billion and more than 90% of Q3 contract value included prepayment terms. They say customer prepayments and financing backed by investment-grade customer contracts are expected to cover about 80% of 2027 capital expenditure. Verify the definitions, periods, and exact percentages in the company’s release and earnings-call transcript; the posts do not establish that prepayments alone fund all capital spending, according to @StockSavvyShay.
The Japanese-language post attributes deployment delays at Vineland, New Jersey, to a gap between reduced temporary power from DataOne and the ramp-up of Bloom Energy fuel cells, and says Microsoft supply continues in stages rather than being canceled. It also reports a reduced 2026 revenue outlook of $3.0 billion to $3.2 billion, a delay of the above-$7 billion annualized revenue target to February 2027, and a 2027 revenue goal of $12 billion to $13 billion with pretax breakeven targeted in Q4. Check these claims, including the sites and customer arrangements, against Nebius’s earnings materials and call transcript; the post itself is not independent confirmation, according to @wallstengine.
The same post reports capital expenditure of about $27 billion in 2026 and $40 billion to $45 billion in 2027, with 75% to 85% of 2027 spending expected to be funded by customer prepayments and financing secured by contracts or assets. It also describes $325 million of nonrecurring revenue, $7.3 billion of equipment and intangible-asset purchases, and a plan to shift most of roughly 1 GW of additional capacity to company-developed sites. These amounts, the revenue classification, and the financing and construction plans are key claims to verify in the primary materials, according to @gwYXhEqd7kjpwYu.